The design & build of the process package of the Sinnamary biomass plant for VOLTALIA

BOCCARD & BERKES are proud to be selected by VOLTALIA for the design & build of the process package of the Sinnamary biomass plant in French Guyana.

The new biomass power plant, with a capacity of 10MWe (40MWth), is located near the Petit-Saut dam in Sinnamary, French Guyana.

EPC contract in the Voltalia Cacao Biomass power plant, French Guiana

The EPC contract includes the engineering, procurement, construction and commissioning of the boiler island, the water/steam cycle including the turbine and its utilities, as well as the high and low voltage electrical equipment and control of the unit.

Extension and revamping of a fresh cheese factory

Expanding a factory is limited by the space available. Our teams designed this new production line by rethinking the layout of the plant.

Revamping of the SUEZ Rambervillers incineration unit (Vosges, France)

On this project, the Boccard teams were entrusted with the realization of the Turbine and Steam Cycle lot.

 

Manufacturing of skids for a uranium mining project in Nigeria

We carried out the design studies as well as the fabrication of four stainless steel skids for one of the largest open pit uranium mining complexes in the world.

Restart of the Arcelor Mittal Galati blast furnace in Romania

The Romanian sheet and plate producer ArcelorMittal Galati has called on Boccard's teams to restart its blast furnace number 5.

Studies of cooling circuits as part of the refurbishment of the B Arcelor Mittal blast furnace in Ghent, Belgium.

ArcelorMittal in Ghent has 2 blast furnaces which are the heart of their production. The blast furnaces operate for 20 to 25 years, after which the refractory lining must be renewed. Today it is the turn of blast furnace B to undergo such an operation.

Piping construction on an oil rig in Malaysia

This construction and installation project of 14,000 tons of piping mobilized up to 400 people for 20 months, including 800,000 hours of work without any accident.

Studies and construction of piping for the nuclear island of the Flamanville EPR

The manufacturing capacity and assembly resources, the quality monitoring and the skills in management of large projects with high modification rates have been the keys to Boccard's success.

EPC fluid package for the Jules Horowitz experimental nuclear reactor

Boccard is in charge of the EPC Fluids lot: design, studies, implementation and start-up of the fluid systems.